Broward.org Mobile
Skip navigation links
Broward Home
Commission
Living
Doing Business
Visiting
Employees
Skip navigation links
Project Description
Project History
Project Timeline
Project Facts
Maps and Renderings
Parking/Traffic Announcements
Photo Gallery
Gallery 1
Gallery 2
Gallery 3
Gallery 4
Gallery 5
Related Projects
Project Timeline
Broward County > New Courthouse > Project Timeline

Winter 2012/2013

January 2013 Install deep injection wells
Install concrete auger cast piles for the Bridge
Start Tower foundations
Erect Tower cranes
December 2012

Install Tower crane pads
Dewatering and sheet piles
Mobilize Tower cranes
Install new drainage along Courthouse Drive

December 18, 2012 Precast plant quality assurance/quality control site visit
December 5, 2012 Demo existing drainage along Courthouse Drive

 

Fall 2012

Nov.-Dec. 2012 Mobilize activities: James A. Cummings (contractor) and Owner’s Construction Project Manager (the Weitz Company) 
Install concrete auger cast piles for Tower
Modify existing 12” water main along Courthouse Drive (added scope)
November 26, 2012

Install new 16" water main along S.E. 6th Street

November 19, 2012 Demo existing duct bank, vault, sidewalk and water main along Courthouse Drive
November 12, 2012 Reconfigure Maintenance of Traffic on 6th Street
Install new sanitary sewer along Courthouse Drive
October 15, 2012 Contractor receives Second Notice to Proceed on elevated walkway between the Courthouse and North Wing building and new elevator core for the west building
October 8, 2012 Install steel sheet piles along Courthouse Drive
September 7, 2012 Install concrete test piles
September 4, 2012 Erect mobile crane for foundation pile work
September 1-28, 2012 Begin FPL underground electrical work along Courthouse Drive

Summer 2012

August 22, 2012 Begin demolition of West Parking Garage
August 21, 2012

First Notice to Proceed issued for new Tower 

August 21, 2012 Groundbreaking ceremony held
August 20, 2012 Plaza area and pedestrian walkway demolished
August 18, 2012 Install temporary fencing around garage perimeter. Close plaza area.
August 2, 2012 Close West Parking Garage
August 1, 2012 First Notice to Proceed issued for garage demo
July 2012 Initial agreements negotiated and signed

Spring 2012

June 12, 2012 Broward County Commission awards construction contract to James A. Cummings, Inc.
May 25, 2012

Final set of design plans submitted by The Spillis Candela & Partners/Heery/Cartaya Joint Venture, the project's design consultant


Please note that dates are subject to change.


Switch to Full Site   | Terms of use
Official Mobile Website of Broward County, Florida
The version of this site is best viewed on a mobile device.