February

Fabrication of architectural precast panels, detention doorframes, and curtain walls system begins

City of Fort Lauderdale bags parking meters at Sixth Street to help mitigate traffic and promote pedestrian safety

January Install deep injection wells
Install concrete auger cast piles for the Bridge
Start Tower foundations
Erect Tower cranes
December 2012

Install Tower crane pads
Dewatering and sheet piles
Mobilize Tower cranes
Install new drainage along Courthouse Drive

Dec. 18 Precast plant quality assurance/quality control site visit
Dec. 5 Demo existing drainage along Courthouse Drive