The Municipal Five-Year Plan includes recommended funding for subsequent phases of capital projects approved by the County Commission in Cycle 1 (2020) for planning and design phases. In addition, the plan reflects the removal of projects by sponsors (municipalities) as well as projects moved ahead of schedule due to efficiency and cost-saving considerations.
The Second Amendment to the Interlocal Agreement guarantees a Minimum Annual Guarantee (MAG) funding commitment to utilize at least ten percent (10%) of the Transportation Surtax Proceeds received by the County each Fiscal Year to fund Community Shuttle Service, Municipal Capital Projects, Municipal R&M Projects, and Municipal Project Contingency.
Active and Upcoming Municipal Surtax Project Solicitations
(as of December 11, 2024)
Deerfield Beach
| DEER-005/006
| Pioneer Grove Improvements
| Construction
| $2,199,903.27
| Executed-Project Underway
| Open Bid
| Link
|
Pembroke Park
| PPRK-002
| S.W. 25th St. Stormwater Impr. (Ph II)
| Construction
| $1,272,115
| In Progress
| Upcoming Solicitation
|
|
Hallandale Beach
| HALL-026
| City-wide Bus Stops Digital Signage
| Construction
| $513,600
| In Progress
| Upcoming Solicitation
|
Link
|
Hallandale Beach
| HALL-005
| City-Wide Bus Shelter Improvements
| Construction | $2,977,563
| In Progress
| Upcoming Solicitation
| Link
|
Miramar
| MIRA-025
| Pembroke Road Bike Lane
| Construction
| $1,848,000
| In Progress
| Upcoming Solicitation
| Link
|
Miramar
| MIRA-020
| Bus Shelter Improvements
| Construction
| $1,056,000
| In Progress
| Upcoming Solicitation
| Link
|
Sunrise
| SUNR-025.1
| Various Drainage Improvements
| Construction
| $5,180,000
| In Progress
| Upcoming Solicitation
| Link
|
West Park
| WPRK-002
| State Road 7 Roadway and Pedestrian Lights (Only restoration work will be solicited)
| Construction
| $437,194.94
| Executed - Project Underway
| Upcoming Solicitation
|
Link
|
West Park
| WPRK-003
| SW 48 Avenue Complete Street
| Construction
| $3,080,000
| In Progress
| Upcoming Solicitation
|
Link
|
Weston
| WEST-303
| Weston Road Corridor Improvements
| Construction
| $4,312,000
| In Progress
| Upcoming Solicitation
| Link
|
West Park
| WPRK-003
| SW 48 Avenue Improvements
| Construction
| $3,080,000
| Executed- Project Underway
| Upcoming Solicitation
| Link
|
Notes:
- Information provided as of December 2024
-
Project Funding Agreement (PFA) Status
- In Progress: Surtax Legal Counsel Team has received all required information and project documentation is under review. May require additional municipal submissions and actions.
- Executed – Project Underway: Agreements have been finalized and projects’ current phases are in progress.
-
Solicitation Status:
- Open Bid: Municipality has an open bid