Municipal Project Information

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​

​​​​The Municipal Five-Year Plan includes recommended funding for subsequent phases of capital projects approved by the County Commission in Cycle 1 (2020) for planning and design phases. In addition, the plan reflects the removal of projects by sponsors (municipalities) as well as projects moved ahead of schedule due to efficiency and cost-saving considerations.

The Second Amendment to the Interlocal Agreement guarantees a Minimum Annual Guarantee (MAG) funding commitment to utilize at least ten percent (10%) of the Transportation Surtax Proceeds received by the County each Fiscal Year to fund Community Shuttle Service, Municipal Capital Projects, Municipal R&M Projects, and Municipal Project Contingency.


The rolling Five-Year Plan is under construction and will be posted after County Commission budget approval in September 2024. 

For a copy of the latest approved plan, email mapsocial@broward.org.


Active and Upcoming Municipal Surtax Project Solicitations (as of August 21, 2024)​


​Municipality
​Project ID
​Project Name
Funded Phase
Surtax Award 
​PFA Status​
​Solicitation 
Status
​More Information
​Pembroke Park
​PPRK-002
​S.W. 25th St. Stormwater Impr. (Ph II)
​Construction
$1,272,115
In Progress
​Pending Solicitation
​Oakland Park
​BC-OAKLAND-FY2020-00002
Stormwater Pump Station and Pipeline Improvements in the North Andrews Garden Neighborhood 
​Construction
​$1,407,661
​Executed - Project Underway​
Bid Open
​Link​

​Davie
​DAVI-012
​​SW 30th Street Improvements
​Construction
​$1,760,000
​In Progress
​Pending Solicitation
​​Link
​Hallandale Beach

​HALL-026
​City-wide Bus Stops Digital Signage
Construction
​$513,600
In Progress​
​Pending Solicitation


​Hallandale Beach
​HALL-005
​City-Wide Bus Shelter Improvements
Construction​​$2,977,563
​In Progress
​Pending Solicitation
​​Link
Fort Lauderdale
​FORT-122
​NW 15th Ave Safety and Mobility Improvements & Street Lighting
​Construction
​$2,996,668
​Executed - Project Underway
​Open Bid
Link

​Miramar
​MIRA-025
​Pembroke Road Bike Lane
​Construction
​$1,848,000
​In Progress
​Pending Solicitation
Link
​Sunrise
​SUNR-025.1
​Various Drainage Improvements
​Construction
​$5,180,000
​In Progress
​Pending Solicitation
​​Link

​West Park
​WPRK-002
​State Road 7 Roadway and Pedestrian Lights (Only restoration work will be solicited)
​Construction
​$437,194.94​
​Executed - Project Underway
​Pending Solicitation
​Link

​West Park
​WPRK-003
​SW 48 Avenue Complete Street
​Construction
​$3,080,000
​In Progress
​Pending Solicitation
Link
​Wilton Manors
​WILT-013
​Electronic Message Boards / Wayfinding​
​Construction
$639,650​​Executed- Project Underway ​
​Pending Solicitation

Notes:

  • ​Information provided as of August 2024​
  • Project Funding Agreement (PFA) Status​
  • ​In Progress: Surtax Legal Counsel Team has received all required information and project documentation is under review. May require additional municipal submissions and actions.
  • Executed – Project Underway: Agreements have been finalized and projects’ curre​nt phases are in progress. 
    • Solicitation Status:
      • ​Bids Under Evaluation: Bidding window closed, and municipality is reviewing bids
      • Open Bid: Municipality has an open bid 
      • Pending Solicitation- Municipality will be posting solicitation soon