Municipal Project Information

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​

​​​​The Municipal Five-Year Plan includes recommended funding for subsequent phases of capital projects approved by the County Commission in Cycle 1 (2020) for planning and design phases. In addition, the plan reflects the removal of projects by sponsors (municipalities) as well as projects moved ahead of schedule due to efficiency and cost-saving considerations.

The Second Amendment to the Interlocal Agreement guarantees a Minimum Annual Guarantee (MAG) funding commitment to utilize at least ten percent (10%) of the Transportation Surtax Proceeds received by the County each Fiscal Year to fund Community Shuttle Service, Municipal Capital Projects, Municipal R&M Projects, and Municipal Project Contingency.


Click to View the Surtax Funding Plan (FY 2020 to FY 2029​)


Active and Upcoming Municipal Surtax Project Solicitations (as of December 11​, 2024)​


​Municipality
​Project ID
​Project Name
Funded Phase
Surtax Award 
​PFA Status​
​Solicitation 
Status
​More Information
​Deerfield Beach
​DEER-005/006
​Pioneer Grove Improvements
​Construction
​$2,199,903.27
​Executed-Project Underway
​Open Bid
​​Link​
​Pembroke Park
​PPRK-002
​S.W. 25th St. Stormwater Impr. (Ph II)
​Construction
$1,272,115
In Progress
Upcoming Solicitation


​Hallandale Beach

​HALL-026
​City-wide Bus Stops Digital Signage
Construction
​$513,600
In Progress​
Upcoming Solicitation
Link​

​Hallandale Beach
​HALL-005
​City-Wide Bus Shelter Improvements
Construction​​$2,977,563
​In Progress
Upcoming Solicitation
​​Link


​Miramar
​MIRA-025
​Pembroke Road Bike Lane
​Construction
​$1,848,000
​In Progress
​Upcoming Solicitation
Link
​Miramar
​MIRA-020
​Bus Shelter Improvements
​Construction
​$1,056,000​
​In Progress
Upcoming Solicitation
Link
​Sunrise
​SUNR-025.1
​Various Drainage Improvements
​Construction
​$5,180,000
​In Progress
Upcoming Solicitation
​​Link
​West Park

​WPRK-002
​State Road 7 Roadway and Pedestrian Lights (Only restoration work will be solicited)
​Construction
​$437,194.94​
​Executed - Project Underway
​Upcoming Solicitation
​Link

​West Park
​WPRK-003
​SW 48 Avenue Complete Street
​Construction
​$3,080,000
​In Progress
Upcoming Solicitation
Link

​Weston
​WEST-303
​Weston Road Corridor Improvements
​Construction
​​$4,312,000
​In Progress
Upcoming Solicitation
Link
​West Park
​WPRK-003
​SW 48 Avenue Improvements
​Construction
​$3,080,000
Executed- Project Underway ​
Upcoming Solicitation
Link

Notes:

  • ​Information provided as of December 2024​
  • Project Funding Agreement (PFA) Status​
  • ​In Progress: Surtax Legal Counsel Team has received all required information and project documentation is under review. May require additional municipal submissions and actions.
  • Executed – Project Underway: Agreements have been finalized and projects’ curre​nt phases are in progress. 
    • Solicitation Status:
      • Open Bid: Municipality has an open bid 
      • Upcoming Solicitation: Municipality may post solicitation within the next 6 months